Facilities Planning
Always Looking to the Future
Protecting clean water is a long-term commitment. As the public wastewater utility serving Eugene and Springfield, MWMC plans decades into the future to ensure the regional wastewater system can continue protecting public health, supporting a growing community, and keeping the Willamette River clean. Facilities planning provides the roadmap for those future investments and improvements.
Current Work: 20-Year Comprehensive Facilities Plan
Latest updates
May 8, 2026: Process Facilities Plan submitted to Oregon Department of Environmental Quality for review and approval
April 10, 2026: Pre-Adoption presentation made at the April MWMC meeting covering Volume 1: Process Facilities Plan
The MWMC Wastewater Comprehensive Facilities Plan identifies and addresses wastewater system improvements needed to continue safe and reliable service to the area for the next 20 plus years. The facilities plan will provide a clear understanding of the capital improvements needed for the wastewater system and how they will be financed.
To take a deeper dive, check out the FAQ page below:
Volume 1
Process Facilities Plan
Volume 2
Integrated Plan
In development – a strategic roadmap for the utility’s future.
Volume 3
Opportunities Plan
In development – aligning programs with our objectives.
Benefits of Facility Planning
- Helps gain access to state and federal funding opportunities.
- Aligns wastewater treatment needs with community goals.
- Forecasts future needs and helps anticipate necessary construction.
- Identifies most cost-effective solutions to wastewater and community needs.
years of forward-looking planning, with reviews every cycle.
A History of Facility Planning
1977 – The 208 Plan
Planning for a regional wastewater system began in the 1970s as local leaders worked together to serve the growing Eugene-Springfield area. The resulting 208 Plan, named for Section 208 of the Clean Water Act, evaluated long-term wastewater treatment needs, compared treatment options, and established a roadmap for future infrastructure investments.
1979–1984 – Building the Regional Treatment Facility
Construction of the MWMC regional wastewater treatment facility began in 1979, and the plant began operating in 1984. The facility was designed to provide reliable wastewater treatment for the Eugene-Springfield region while protecting public health and the Willamette River.
1990s – Planning for Future Growth
As the region continued to grow, MWMC completed a Master Plan to evaluate how the treatment facility was performing compared to its original design. The study recommended additional planning to address increasing wet weather flows and biosolids processing, leading to development of the Wet Weather Flow Management Plan in 1997.
2004 – Comprehensive Facilities Plan
MWMC completed its first comprehensive Facilities Plan following review by the Oregon Department of Environmental Quality (DEQ). The plan evaluated existing infrastructure, projected future wastewater needs, and identified projects to help ensure reliable treatment capacity for decades to come.
2014 – Partial Facilities Plan Update
A decade later, MWMC completed a Partial Facilities Plan Update to evaluate changing regulations, new data, and future planning priorities. While not a complete rewrite of the 2004 plan, it provided the technical foundation for planning decisions leading up to the next wastewater discharge permit renewal.
2022–Present – Planning for the Next Generation
After renewing its National Pollutant Discharge Elimination System (NPDES) permit in 2022, MWMC began developing the next generation of its Facilities Plan. The updated plan will help guide future investments in treatment facilities and infrastructure while preparing the regional wastewater system to meet future community needs and environmental regulations.