History

MWMC History

The MWMC was formed in 1977 through an intergovernmental agreement between Lane County and the cities of Eugene and Springfield. The MWMC was created to construct and operate the regional wastewater facilities for the Eugene-Springfield area.

1950
1950

Eugene and Springfield dispose of wastewater directly to the Willamette River.

1972
1972

Clean Water Act passes, establishing new requirements for wastewater treatment.

1977
1977

City officials decide a new regional treatment facility is needed to provide for the wastewater disposal needs of the growing region; MWMC is formed.

1979
1979

Groundbreaking begins for the regional wastewater treatment facility.

1984
1984

New wastewater treatment facility comes online.

1989
1989

Biosolids Management Facility begins operation.

1997
1997

Complete the Water Pollution Control Facility Master Plan, which initiates the Facilities Planning Process.

2000
2000

Biosolids Dewatering Facility constructed.

2001
2001

Wet Weather Flow Management Plan is developed.

2004
2004

  • The Commission adopts the “Facilities Plan,” a roadmap to meet the community’s wastewater needs until the year 2025.
  • First phase of three phases of poplar trees is planted at the Biocycle Farm.

2006
2006

Major construction begins at the treatment facility to deliver on “Facilities Plan” improvements.

2008
2008

  • The clarifiers, where solids settle out of the wastewater, were expanded to ensure the treatment facility could handle severe wet weather flows, and to improve the treatment process.
  • Three existing digesters, which treat solid by-products, were retrofitted with improved tank mixing technology.
  • New liners of high-density polyethylene were installed in four lagoons.

2009
2009

Aeration Basins are used to reduce organics in wastewater treatment.

2010
2010

  • Several upgrades (covers, filters, and fans) were made to capture and treat even more odors at the facility. This is part of our Good Neighbor Policy.
  • A conversion to a Sodium Hypochlorite system increased disinfection capacity from 175 million gallons per day (mgd) to 277 mgd to meet peak flow capacity requirements.
  • Peak Flow Management introduced to increase facility capacity by routing wastewater through an alternative process configuration during high flows.
  • Completed influent pumping and headworks expansion project, allowing more flow to enter the plant during wet weather, high-flow events.

2013
2013

Digester capacity improved with introduction of primary sludge thickening process.

2015
2015

New access locations for inspection and maintenance of the piping system was added to the biosolids pipeline that connects the wastewater treatment facility to the Biosolids Management Facility.

2017
2017

Started construction on a fourth digester to increase capacity. Additionally, started construction on new maintenance buildings, that include the water quality testing lab. These buildings are 30 plus years old. The uses of these buildings have changed substantially due to advances in technology, increasing stringent environmental regulations and changes in staffing levels to meet regulations.

2021
2021

Began operating a Renewable Natural Gas facility, which cleans biogas from the anaerobic digesters and converts it to commercial-grade natural gas. The gas is then injected into NW Natural’s pipeline, where it is used as a renewable fuel source.